Killingly · Project Husky

The Project Husky timeline

Every confirmed date, decision and hearing so far — and what comes next.

  1. Filing

    Traffic and stormwater studies in PZC packet

    The developer's Langan traffic study and stormwater report appear in the Planning & Zoning Commission meeting packet.

    Source
  2. Decision

    PZC approves warehouse moratorium

    Planning & Zoning approves a town-wide moratorium on new warehouse and distribution applications.

    Source
  3. Decision

    Wetlands permit denied 3–2

    The Inland Wetlands commission denies the first application, without prejudice, finding alternatives weren't shown.

    Source
  4. Filing

    Revised application filed

    Ryan Companies files a smaller, revised plan — four days before the moratorium takes effect.

    Source
  5. Decision

    Moratorium takes effect

    Runs through June 30, 2027. It does not cover the July 16 application.

    Source
  6. Decision

    Wetlands commission accepts new filing

    Unanimously accepted; public hearing set for September 14.

    Source
  7. Hearing

    Wetlands public hearing opens

    Residents raise concerns; the hearing is continued.

    Source
  8. Hearing

    Planning & Zoning public hearing

    Scheduled PZC public hearing on the project.

    Source
  9. Hearing

    Wetlands hearing continued again

    Three-hour session; residents' engineer testifies. No decision; continued to November 2.

    Source
  10. Next up

    Next wetlands hearing

    Hearing continues; intervenor status expected to be decided.

    Source

Dates can move

Hearings are often continued. Confirm on the town's agendas and minutes before you go. The developer's court appeal of the July denial is pending — follow the appeal.