QCQuiet Corner Brief

Killingly · Project Husky

The court appeal

The developer is appealing the July wetlands denial. Here is what is confirmed — and what isn't yet.

Status: pending

We have not yet confirmed the court, docket number, filing date, hearing dates or the arguments in the appeal. We will add each one here, with its source, as soon as it is confirmed from court or town records. Nothing on this page is guessed.

How we got here

  1. Wetlands permit denied 3–2

    The Inland Wetlands commission denies the first application, without prejudice, finding alternatives weren't shown.

    Source
  2. Revised application filed

    Ryan Companies files a smaller, revised plan — four days before the moratorium takes effect.

    Source
  3. Wetlands commission accepts new filing

    Unanimously accepted; public hearing set for September 14.

    Source

Arguments

The town's stated reason for the July 6 denial was that alternatives weren't shown. The developer's arguments on appeal will be summarized here once we can read the filed complaint.

Follow the case yourself